The HRP is also a funds raising appeal document, where funding requirements of each cluster are presented separately and consolidated to form the total funding requirement for the response. Each sector coordinator is responsible to estimate the budget needed to implement the sectorial strategy for the coming year/phase. This is a complicated task as many parameters must be considered, and many variables are still unknown during planning phase (material cost, logistic cost...), which can change the overall budget. Nevertheless, response costing must be done quickly enough for funding to be allocated without delay. Even when costs are roughly estimated, it is important to be transparent and be able to explain how it was calculated. Cluster response budgets also represent targets against which funding allocation level will be regularly measured. Such monitoring of the funding status is used to advocate for further efforts in resource mobilization throughout the response.
Response costing method |
As shown in the diagram above, there are two ways for WASH Cluster coordinators to estimate WASH response budget:
1- Indirect costing: In protracted emergencies (usually around September), partners are requested to upload a summary of their planned projects for the next year on the OPS website. Cluster coordinators can be asked to pre-validate projects on OPS to make sure they meet minimum criteria. Operational Response Plan’s costs can be calculated by adding up requested budgets from all approved partner’s planned proposals. The positives and negatives aspects of this method include:
-Partners have tendency to overestimate their funding requirements, and not factor in difficult access, or their capacity gap
-Difficult to estimate geographic/program overlapping. Partners will not do it between themselves, as they are in competition for funding
-Subjective, based on partner’s estimation
2- Direct costing: The WASH Cluster coordinator use caseload figures, priority activities and unit costs to estimate total response budget themselves. Activities/beneficiaries' unit costs can be estimated directly, or taken from partners’ former projects’ final report (final reports’ budget are preferred to proposal ‘s budget, as costs are more accurate).
|
OPS (Online Project System), where cluster partners are requested to upload a summary of their planned project for next year |